This is topic Construction underway - San Onofre siding in forum Western US at RAILforum.


To visit this topic, use this URL:
http://www.railforum.com/cgi-bin/ultimatebb.cgi/topic/7/410.html

Posted by MPALMER (Member # 125) on :
 
As I drove past San Onofre this morning I saw a construction crew working near the south end of the extended San Onofre siding. [This is on the former AT&SF "Surf Line" in So Cal between Oceanside and San Clemente

Also, there are several signals wrapped in plastic with the signal heads turned. New three-light signals to come on line later this summer?

MP
 


Posted by chrisg (Member # 2488) on :
 
The siding extension is due to be done this weekend. New CP San Onofre is now MP 212.3
We get 3.1 miles of 2MT CTC ATS .


Chris

 


Posted by chrisg (Member # 2488) on :
 
It is now in service. The detector has a male voice saying San Diego Northern now and is good for both tracks.

Chris
 


Posted by MPALMER (Member # 125) on :
 
Glad to hear it (that the siding is open, that is). Can always use more capacity/fewer delays along that line.
 